Contract Claims Management

Construction Management Solutions is a trusted leader in construction claims identification, evaluation and resolution. Our construction claims team specializes in the preparation and analysis of construction claims and disputes for construction and engineering projects throughout California.

Click here to meet one of our claims consulting resources


Construction Claims Management

Regional Plant No.4-Expansion to 14MG
Inland Empire Utilities Agencies

CMS performed in-depth schedule evaluation and analysis of multiple Owner-cause delay events occurring throughout the water treatment plant upgrade project. A "Windows" method schedule analysis was used to successfully negotiate a 400 day compensable contract time extension.

Lancaster Water Treatment Plant Stage 5
LA County Sanitation Districts

CMS evaluated multiple impacts and project delays throughout the $145,000,000 water treatment plant expansion project. A step-by-step "Windows" method schedule analysis was used to effectively demonstrate complex engineering and construction compensable delay issues of over 200 days.

Recycled Water Pipeline Projects
Inland Empire Utilities Agency/Cucamonga Water District

CMS performed in-depth schedule analysis and evaluations of compensable delays occurring across multiple construction projects valued at $5,000,000 (total) within the recycled water pipeline program at IEUA and CWD.

Advanced Water Treatment Facility
Orange County Water District

CMS evaluated multiple impacts and project delays within the $300,000,000 water treatment facility project. CMS' analysis of Owner delays resulted in a successful negotiation of a 162 day contract time extension for the General Contractor.

Perris Plant 4 Expansion
Eastern Municipal Water District

CMS evaluated multiple impacts and project delays for the Agency and helped successfully defend an erroneous $1.5 million dollar extended overhead claim by the General Contractor.

Palmdale Water Reclamation Plant Stage 5 Expansion
LA County Sanitation District

CMS evaluated multiple impacts and project delays to the $120M water reclamation plant expansion project. A step-by-step "Windows" method schedule analysis was prepared to demonstrate complex construction delay issues effective in securing an 120 day contract time extension for the General Contractor.

Queensway Southbound Ramps J&K Over Harbor Scenic Drive
Los Angeles Country Department of Public Works

CMS used forensic project analysis to create baseline schedule and as-built schedule files incorporating multiple delay issues. CMS evaluated both Owner and General Contractor-caused delays and prepared a Time Impact Analysis to help negotiate a 185 working day contract extension for the General Contractor